Update on Avenue works below.
Posted by Highfield Residents' Association on Jul 27, 2021 in Hot Topics, News | 0 commentsNote in Phase 3, which starts from 9 August for up to 3 weeks, works to modify the junction mouth with Westwood Road and install a continuous footway crossing will require the closure of the Westwood Road junction for the duration.
Over the last month, we have been working to install a new toucan crossing and continuous crossings on The Avenue, as well as making junction improvements at Winn Road. We have also been managing the overhanging trees and upgrading street lighting.
This work is progressing well and we are currently on schedule to move on to the next phase of the project from 9 August. You can learn more about the project and each phase on our website: https://transport.southampton.gov.uk/…/the-avenue-phase-4/